| Water project |
Estimated project value |
Stage |
Location |
| Cleaner Seas Alliance – Upgrade of Wastewater Treatment Plants Completion – November 2009 |
120 |
Construction |
Far North |
| Connors River Dam: With a potential storage capacity up to 336,000 ML, the proposed dam will increase the northern Bowen Basin region’s water supply reliability and security. The associated water pipelines are proposed from the dam to the northern Bowen Basin, servicing areas of highest demand for the dam’s stored water. This will help meet the future water demands of industries and communities throughout the region. |
116.5 (60 for pipelines) |
Prefeasibility |
Mackay |
| Thuringowa City Council Wastewater Upgrade Program |
80-120 |
Under Study |
Northern |
| Mt Isa Water Board (Terminal reservoir Pump Station upgrade) |
16.7 |
Construction |
North West |
| Mt Isa Water Board (Lake Moondarra pipeline Stages 1, 1A & 2) |
3.667 |
Construction |
North West |
| Gibson Island Advanced Water Treatment Plant |
254 |
Construction |
SE Queensland |
| Gladstone Area Water Board Fitzroy Pipeline: The pipeline will run underground from the Fitzroy River via an easement, through the proposed Stanwell – Gladstone Infrastructure Corridor (SGIC) and Gladstone State Development Area (GSDA), before finally joining GAWB’s raw water reticulation system. Construction 2009-11. |
372.925 |
Technical Investigation |
Fitzroy |
| Nikenbah Wastewater Treatment Plant: The facility comprises a 10,000 equivalent dwelling wastewater treatment plant (WTP) intended to service Hervey Bay’s western urban catchment for the period to 2023. The design capacity of the plant is 4.8ML per day (average dry weather flow) and will operate using a membrane bioreactor (MBR) process to ensure a high standard of treatment and enhancing reuse opportunities. |
35.6 |
Construction |
Wide Bay-Burnett |
| Rookwood Weir and Eden Bann Weir Government has committed to construction of the new infrastructure by 2011 |
72 (Rookwood)71.33 (Eden) |
Committed |
Fitzroy |
| Traveston Crossing Dam Stage I: Mary River. Staged construction. Stage 1 completion by end of 2011 to delivering 70,00Ml per annum. Stage 2, $250M, raising of the Borumba Dam by 2015. Stage 3, completion of Traveston Dam by 2035. |
1592 |
Under Study |
Wide Bay-Burnett |
| Yeppoon Pipeline Start – early 2008 completion Dec 2009. 33 kilometre water pipeline to supply water to urban users on the Capricorn Coast. Construction of the pipeline will also have significant environmental benefits as it will remove the need to extract water supplies from the Sandy Creek coastal dune system in the future. |
50 |
Construction |
Fitzroy |
| Eastern Pipeline Inter-Connector: a bulk water network that will transport water between Redland Shire and Logan City. The pipeline will be capable of distributing water in either direction. |
38 |
Construction |
SE Queensland |
| Goodna Wastewater Centre Augmentation Project completion – 2012 |
80 |
Construction |
SE Queensland |
| Hinze Dam Raising ( Stage 3) Completion December 2010 |
395 |
Construction |
SE Queensland |
| Merrimac East Project third phase of the Beenleigh-Merrimac-Pimpama wastewater upgrade |
128 |
Construction |
SE Queensland |
| Murrumba Downs Water Pollution Control Works Alliance $52.7M (treatment plant upgrade –$41M. Advanced water factory – $11.7M) |
105.4 |
Construction |
SE Queensland |
| Northern Pipeline Inter-Connector: Stages 1 and 2 will connect dams, weirs and other water storages to move surplus water between Caboolture and the Sunshine Coast. With the potential capacity to transport 65 million litres of potable water per day, the pipeline will link existing and potential future water sources throughout the Sunshine Coast. Stage 1 expected completion Dec 2008. Stage 2 expected start mid 2009. |
849 |
Basic Engineering |
SE Queensland |
| Urannah Dam |
300 |
Under Study |
Mackay |
| Water for Bowen and Extension to Proserpine via new pipelines |
85 |
Feasibility |
Mackay |
| Western Corridor Recycled Water Pipeline: 89% of pipeline and facilities complete; 91% of advanced water treatment plants complete @ 14 Oct 2008. |
2493 |
Construction |
SE Queensland |
| Wyaralong Dam: Due for completion in 2011, the proposed Wyaralong Dam will supply 21,000 ML/a (when operated in conjunction with Cedar Grove Weir). The Project may be delivered a year ahead of schedule, subject to approvals - work could begin early next year and be finished by the end of 2011. |
333 |
Detailed Engineering |
SE Queensland |
| Nathan Dam Development: (inc. pipelines) the project will require assessment and approval under the Environment Protection and Biodiversity Conservation Act 1999 (Cth) before it can proceed |
400 |
EIS |
Darling Downs |
| Toowoomba Pipeline: The proposed 38 km pipeline will run from the Wivenhoe Dam intake point at Paddy Gully Road and continue west past the township of Esk, through the Deowongar State Forest to Cressbrook Dam. The project is required to be completed by late January 2010. Constructiioin start Feb 2009. |
187 |
Detailed Engineering |
Darling Downs-SE Queensland |
| Wetalla pipeline project: capable of delivering recycled water from the Wetalla Wastewater Reclamation plant, directly to the mine |
29 |
EIS |
Darling Downs |