| Australian Inland Rail Expressway (AIRE): Melbourne to Toowoomba inland railway to link Melbourne and Darwin via NSW and Queensland. |
3000 |
Under Study |
Darling Downs |
| Berwyndale to Wallumbilla gas pipeline: operational by Jan 2009 |
70 |
Under Study |
Darling Downs |
| Braemar 2 Gas Pipeline Project: completion February 2009 |
60 |
Construction |
Darling Downs |
| Brigalow to Tarong Rail Line: Subject to feasibility studies and commercial negotiations on alternative coal source options. |
500 |
Under Study |
Darling Downs-Wide Bay-Burnett |
| Cameby Downs Coal Project: new open-cut mine |
100- |
Under Study |
Darling Downs |
| Charlton North Industrial Estate |
18 |
Basic Engineering |
Darling Downs |
| Chinchilla Coal Seam Gas-Fired Power Station (the facility will be Australia's first purpose-built coal seam methane power station, using feedstock from QGC's Surat Basin operations) |
200 |
Pre-feasibility |
Darling Downs |
| Condamine Power Station: CSM Gas fired power station on the CSM gas seam at Berwyndale South. 100 to 160 MW |
200 |
Construction |
Darling Downs |
| Dalby reinforcement of supply (Ergon) |
32 |
Basic Engineering |
Darling Downs |
| Darling Downs Power Station (Ergon Energy gas-fired power station in the Darling Downs region near Braemar, 40km west of Dalby) |
780 |
Construction |
Darling Downs |
| Department of Housing construction medium density Darling Downs |
3.928 |
Committed |
Darling Downs |
| Department of Housing construction detached houses Darling Downs |
2.912 |
Committed |
Darling Downs |
| Elimatta: development of an open-cut, export coal mine, construction 2010. |
500 |
Under Study |
Darling Downs |
| Fairview Power Project new 100 MW gas-fired power station near Injune aims to generate electricity from methane extracted from coal seams located too deep underground to be mined |
445 |
Committed |
Darling Downs-South West |
| Hunter Gas Pipeline Project: Approximately 200 km of the pipeline (total length 850 km) is within Queensland. A major driver of the proposal is to provide the missing link in the east Australian network and provide additional security of gas supply to Sydney and Newcastle. |
700 |
Under Study |
Downs-South West |
| Kogan Creek Power Station (CS Energy property, plant and equipment) |
19.192 |
Ongoing |
Darling Downs |
| Lacerta Coal Seam Gas Project |
67 |
Under Study |
Darling Downs |
| Millmerran - Inglewood Road |
14 |
Basic Engineering |
Darling Downs |
| Nathan Dam Development: (inc. pipelines) the project will require assessment and approval under the Environment Protection and Biodiversity Conservation Act 1999 (Cth) before it can proceed |
400 |
EIS |
Darling Downs |
| New Acland Coal Mine expansion: 14 kilometres north-northwest of Oakey and 35 kilometres northwest of Toowoomba. New Acland Coal Pty Ltd (NAC), the proponent, proposes to develop the New Acland Coal Mine Stage 3 Expansion project. The project involves the progressive expansion of the existing New Acland Coal Mine and associated infrastructure to increase coal production from 4 million tonnes per annum (Mtpa) to 10 Mtpa for the domestic and export markets and to secure a reliable coal supply for a possible future alternative fuels project. |
500 |
Basic Engineering |
Darling Downs |
| New Acland Coal to Liquids Project: Trial of Low temperature coal conversion using US catalysts treating 100,000 tonnes coal per year. |
65 |
Basic Engineering |
Darling Downs |
| New England Highway |
26 |
Committed |
Darling Downs |
| Surat Basin Railway (Southern Missing Link): 207km link the towns of Wandoan and Banana to the Port of Gladstone. Railway is likely to initially consist of single track with passing loops at approximately 25km intervals that will be able to accommodate trains approximately 2.4km in length. Construction will be undertaken with multiple work fronts and require a workforce currently estimated at an average of 400-600 personnel over a duration of approximately two and a half years. |
800-1,000 |
EIS |
Darling Downs-South West-Fitzroy |
| Southern Queensland Institute of TAFE - Toowoomba automotive |
2.645 |
Construction |
Darling Downs |
| Spring Gully Power Station 80 km north-east of Roma. Delayed with construction of Darling Downs Power Station @ Braemar. |
1000 |
On hold |
Darling Downs-South West |
| Sunstate Gas to Liquids Project: World scale project to convert coal seam methane to ultra clean diesel to produce 17,000 barrel per day or six million barrels per year of refined product to cost approximately (AUD) $1.5 billion Expected to begin construction in 2010 and completion 2015 |
1500 |
Feasibility |
Darling Downs |
| Toowoomba Pipeline: The proposed 38 km pipeline will run from the Wivenhoe Dam intake point at Paddy Gully Road and continue west past the township of Esk, through the Deowongar State Forest to Cressbrook Dam. The project is required to be completed by late January 2010. Constructiioin start Feb 2009. |
187 |
Detailed Engineering |
Darling Downs-SE Queensland |
| Toowoomba Reinforcement of Supply |
37 |
Basic Engineering |
Darling Downs |
| Warrego Highway – Toowoomba: Toowoomba Bypass |
10 |
Basic Engineering |
Darling Downs |
| Wallumbilla–Darling Downs Power Station Gas Pipeline: 200km pipeline |
90 |
Under Study |
Darling Downs |
| Warwick Reinforcement of Supply and substation |
49 |
Construction |
Darling Downs |
| Wandoan Coal Project: will comprise the development of thermal coal resources for export markets and possibly domestic markets with an open-cut coal mine and related local infrastructure. The provision of water and power supply to the mine will also be involved. Targets first coal in late 2011. Mine infrastructure for the Project would consist of: accommodation facilities for mine personnel for both the construction and operational phases of the Project; communications infrastructure; light vehicle access roads and heavy vehicle haul roads; a water management system; waste water treatment facilities; fuel and oil storage facilities; high voltage transmission lines/poles and reticulation facilities; maintenance workshop, offices and associated amenities; coal handling and preparation facilities and tailings dams. |
1,000+ |
Basic Engineering |
Darling Downs |
| Wandoan Coal—Electricity Infrastructure: expected completion Dec 2012 |
100+ |
Under Study |
Darling Downs |
| Wetalla pipeline project: capable of delivering recycled water from the Wetalla Wastewater Reclamation plant, directly to the mine |
29 |
EIS |
Darling Downs |
| Yandina Industrial Estate |
6 |
Basic Engineering |
Darling Downs |
| Yarraman - Toowoomba Roadworks |
27 |
Basic Engineering |
Darling Downs |